Construction of the Inguri dam began in 1961. The dam became temporarily operational in 1978, and was completed in 1987. In 1994, the dam was inspected by engineers of Hydro-Québec, who found that the dam was "in a rare state of dilapidation". In 1999, the European Commission granted €9.4 million to Georgia for urgent repairs at the EInguri HES, including replacing the stoplog at the arch dam on the Georgian side and, refurbishing one of the five generators of the power station at the Abkhaz side.
http://users.livejournal.com/schwalbe_/4054.html
0 Комментарии